Illustrative image – not actual.The Union Ministry of Power has decided on a payment security mechanism (PSM) for the Reliance promoted 3,960 MW coal based Hirma power project in Orissa. Lack of a PSM has been holding back the financial closure of the project.
As per the planned PSM, only those states committing to achieve milestones in power sector reforms will be allowed to draw power from the project through Power Trading Corporation (PTC). PTC will buy power from the project and sell it to fives states of Madhya Pradesh (600 MW), Gujarat (720 MW), Rajasthan (1,200 MW), Punjab (940 MW) and Haryana (500 MW). Thus, PTC will have to sign two PPAs, one with the promoter of the project and the other with the states buying power.
The PSM provides for three lines of defence to the promoters. These are:
Ø
The capital base of PTC will be increased from the present Rs.25 crore
to Rs.3,025 crore, through the issue of tax free bonds worth Rs.3,000. This
will make PTC capable of managing electricity bills for six months in case the
states buying power from the project default in their payments.
Ø
The states buying power will extend a letter of credit to PTC amounting
to one and half months’ billing, which would be used in case of default by
them.
Ø
The states buying power from the project through PTC would also have to
extend bank guarantees.
Further, PTC will also be entitled to recover pending bills from the
Central Plan’s allocation to the defaulting states. This is expected to make
the PSM attractive to the lenders.
The proposed PSM will now be placed before the Cabinet for approval.