Dilip Buildcon (DBL) has received the provisional completion certificates for two road projects in Madhya Pradesh.
The company has been issued the provisional completion certificates as declaration of the commercial operation date (COD), prior to the scheduled completion date for the following projects:
1. Development of the Patan - Tendukheda - Rehli road section 31.10 km to 113.00 km (length 86.60 km) state highway no. 15, on design, build, finance, operate and transfer (DBFOT) on toll plus annuity basis, at a cost of Rs 261.28 crore. The scheduled completion period for the project was 730 days from the appointment date. The company completed the project in 356 days and the commercial operation date was 31 March, 2017.
2. Rehabilitation and upgradation of Jabalpur - Mandla - Chilpi section of NH-12A from 477.60 km of NH-7 to 12.60 km of NH-12A upto 22.80 km on NH-12A (length 21.85 km) under NHDP-IV (Package-I), on engineering, procurement and construction (EPC) basis. The cost of the project was Rs 201.06 crore. The scheduled completion period for the project was 730 days from the appointment date. However, the company completed the project in 630 days. The commercial operation date was 17 February, 2017.
The company is entitled to receive a maximum bonus amount of Rs 42.18 crore in view of earlier completion of the road projects.