Provisional completion certificate issued to DBLIllustrative image – not actual.

Dilip Buildcon (DBL) has received the provisional completion certificate for Hassan- Remanathapura-Periyapaha road project in Karnataka.

The project envisages design, build, finance, operate, and transfer (DBFOMT) of Hassan-Remanathapura-Periyapaha in Karnataka on hybrid annuity basis. The company completed the project 212 days prior to the scheduled completion date. The project was completed in 730 days from the appointed date.

The road project has been declared fit for entry into commercial operation as on 28 February 2018. The cost of the project is Rs 254.61 crore and had a scheduled completion date of 28 September 2018. The provisional completion date of the project was 28 February 2018.

The company is entitled to receive maximum bonus of one annuity payment of Rs 26.28 crore.