Dilip Buildcon (DBL) has received provisional completion certificate from the government of India, Ministry of Road Transport & Highways (MoRTH).
The project rehabilitation and upgradation of Eeppurupalem-Ongole Section from 195.000 km to 254.500 km/design ch 184.910 km to 242.784 km of NH-214A (new NH-216) to two-lane with paved shoulder in Andhra Pradesh under NHDP -IV on EPC basis has been provisionally completed.
The cost of the project is Rs 350.01 crore.
The provisional completion certificate has been issued by the authority on 17 August 2019 and has declared the project fit for entry into operation as on 20 July 2019.