A provisional certificate has been issued to IRB Infrastructure Developers’ wholly-owned SPV Kaithal Tollway for the Kaithal Rajasthan border project, effective 6 September 2017.

The road project is for four laning of the Kaithal Rajasthan border section of NH-152/65 from 33.250 km to 241.580 km (design length 166 km) in Haryana.

The project is being executed as build, operate, transfer (BOT) (Toll) on design, build, finance, operate and transfer (DBFOT) pattern under NHDP Phase-IV.

Of the design length of 166 km, 144 km has been completed, which is around 87 percent of the design length.

The concession period of the project is 27 years, including construction period of 2.5 years. The cost of the project is Rs 2,290 crore.

The SPV has commenced partial toll collection on the project from 8 September 2017 -- four months ahead of the scheduled commercial operation date.

 