Weekly Round-up: May 22-28, 2005

Every Saturday, ProjectsToday would bring together important project-related developments transpiring in the Weekly Round-Up. These developments will be presented as information nuggets with relevant hyperlinks leading you to more details available in the sections, Project News, Projects Information and Project Tenders. The entire compilation has been organized in subjects to facilitate reference. The following report pertains to the period 22 May 2005 to 28 May 2005.

Financial closure

  • Mumbai Integrated SEZ (MiSEZ), the merged project of Cidco's Navi Mumbai SEZ and Sea King Infrastructure's Maha Mumbai SEZ, has achieved financial closure on 25 May 2005. (more news, project details)

Response to tenders

  • Petronet LNG, in its board meeting held on 24 May 2005, pre-qualified four bidders--IHI
    Consortium of Japan, Technigas of France, Sofregaz of France/ Italy and Tractebel of   Belgium, for awarding  the EPC contract for 2.5 million tpa LNG terminal in Kochi. (more news, project details) 

MoUs signed

  • The MoU for Posco's proposed 12 million tpa integrated steel plant in Orissa would be signed in the first week of June 2005. (more news, project details)

Expected commencement of work

  • KG basin production to start in 2008 (more news)

Project impediments

  • Delay foreseen in NHDP-Phase II (more news)

Other developments

  • Investment Commission to pursue Posco project, others (more news)

  • Posco chief meets Orissa CM: MoU "soon" (more news)

  • VW team meets Andhra CM: No decision yet (more news)

  • VW team studies sites in Vizag (more news)

  • CoPT to allot land to GAIL for ethane unit (more news) 

  • IL&FS in pact with West Bengal (more news)

  • Following increase in steel prices, Kochi Refineries is expecting a cost escalation in its
    Rs.780 crore single buoy mooring project in Kerala. The project management consultant, Intek Asia-Pacific, is expected to submit the revised cost estimate report by June 2005. (more news, project details)

  • VW delegation to meet Andhra CM today (more news)

Completion of projects

  • It was learnt that construction of the residential complex (Phase I and Phase II) Gayatrilok
    of Capital Hotels & Developers in Hardwar district of Uttaranchal was completed in April 2005. (project details)

  • On 23 May 2005, India's first six lane BOT toll road project and the single largest BOT highway project -- Jaipur-Kishangarh project was dedicated to the nation at the hands of Dr. Manmohan Singh, Hon'ble Prime Minister of India. The Rs.614 crore 90 km. project, build through a special purpose vehicle--GVK Jaipur-Kishangarh Expressway Pvt. Ltd.- was completed in 24 months, six months ahead of schedule. (more news, project details) 

  • It was learnt that Murudeshwar Ceramics's Rs.40.36 crore vetrified tiles plant project at
    Karaikal in Pondicherry, completed its phase II with a capacity of 12,000 sq mtr/day in October 2004.(project details)

  • Chief Minister of Himachal Pradesh, Mr. Virbhadra Singh, inaugurated Hindustan Lever's Rs.110 crore soaps and detergents manufacturing facility at Barotiwala in Solan district. HLL's soaps project will have the capacity to annually produce 1,10,000 tonnes of soaps and detergents. (project details)

  • SRF's Rs.17 crore belted fabrics expansion project commenced commercial production with capacity raised from 5,000 tpa to 7,500 tpa. The plant is located at Viralimalai in Tiruchchirappalli district of Tamil Nadu. (project details)

  • The Rs.110 crore calcined petroleum coke expansion project of Rain Calcining in Visakhapatnam district of Andhra Pradesh commenced commercial production on 23 May 2005. The plant capacity has been scaled up to 480,000 tpa. (project details)

Envisaged completion of projects

  • Work on the first unit of 50 MW of Karbi Langpi Hydel Power Project being implemented by Assam State Electricity Board was likely to be completed by March 2006 and the second unit of 50 MW by December 2006.(project details)

  • The Rs.100 crore-300 tpd sponge iron project of Shyam Steel at Durgapur in Bardhaman district of West Bengal is expected to be complete by July 2005.(project details)

Organic Indian Investment Abroad

  • Coromandel Fertisers to set up JV in Tunisia (more news)

  • IOC to acquire 50 per cent stake in Turkish refineries (more news)

  • CIL to acquire new blocks in Indonesia (more news)

Long-term Investment Plans

Project Financing

  • ADB to lend Rs.900 crore to NE states (more news)

  • DPSC plans Rs.200 crore expansion, scouts investors (more news)

  • Krishna Knitwear Technology's Rs.600 crore cotton textiles expansion project is likely to
    commence by August 2005 with completion scheduled for March 2007. The project will be financed to the extent of 70 per cent through borrowings under the Textile Upgradation Fund (TUF) scheme and 30 per cent through internal accruals. (more news, project details)

New Projects
(List is not exhaustive, for full list of projects added, please use Advanced Search of Projects Information Section)

  • Bombay Rayon to set up manufacturing unit in Karnataka (more news)

  • NTPC, DMRL to develop gas turbine blades (more news)

  • IOC-Petronas venture to expand LPG business (more news)

  • ONGC to invest Rs.2,800 crore in Bassein field (more news)

  • ELF Gas plans 50 LPG outlets in South India (more news)

  • DVC plans new dam project in Jharkhand (more news)

Policy Developments

  • Civil aviation: No plan to hike FDI limits (more news)