Every Saturday, ProjectsToday brings together important project-related developments transpiring during the week, in the Weekly Round-Up. These developments are presented as information nuggets with relevant hyperlinks leading you to more details available in the sections -- Project News, Projects Information and Project Tenders. The entire compilation has been organized in subjects to facilitate reference. The following report pertains to the period  22-28 July 2007.

New Projects
(To view new projects added during the period 22 - 28 July 2007, click here)

  • MRF plans manufacturing unit in Tamil Nadu (more news)
  • CHB plans 2,500 houses in Naya Raipur (more news)
  • KSEB plans thermal power plant in Orissa (more news)

  • IOC plans second paraxylene plant (more news)
  • Mantri Realty plans 540 MW power plant in Maharashtra (more news)
  • RIL plans 4,000 MW gas based power plants (more news)

Approvals, Clearances

  • Surat Agriculture Produce Market Committee received all the necessary approval from the government for the Rs.500 crore agro food park project in Surat district of Gujarat. The company is in the process of finalising contractor and architect. Financial closure is expected by September 2007. (project details)
  • The Ministry of Environment & Forests accorded clearances to West Coast Paper Mills' Rs.1,100 crore 1.2 lakh tpa paper & paper board expansion project at Dandeli in Uttara Kannada district of Karnataka. (project details)

MoUs signed

  • GAIL, ONGC signs MoU for gas pipeline joint venture (more news)
  • NTPC signs MoU with ADB for renewable power generation (more news)
  • Railways ink MoU with Kirloskar to develop road railers  (more news)

Foundation stone laying

Commencement of work

  • Work on captive power unit (2x18 MW), part of JK Lakshmi Cement's 0.6 million tpa cement expansion project in Sirohi district of Rajasthan began. (project details)
  • Work on Posco India's steel plant at Paradip in Orissa is expected to commence by December 2007. Land acquisition and mining leases was likely to be completed by October 2007. (project details)

  • On 28 June 2007, Leader of the Opposition Mr. L K Advani inaugurated Madhya Pradesh State Electricity Board's Rs.2,066 crore Sanjay Gandhi power project (Stage II) at Birsinghpur in Umaria district of Madhya Pradesh. (project details)
  • K S Oils' Rs.27 crore 4.5 MW wind based power project in Kachchh district of Gujarat was completed. (project details)
  • RKKR Steel Group is likely to commence work on Phase I of steel plant in Nellore district of Andhra Pradesh by September 2007.(project details)

Commencement of work (Envisaged)

  • Work on Kerala Industrial Infrastructure Development Corporation's Rs.60 crore biotechnology park at Kalamassery near Kochi in Ernakulam district of Kerala is likely to commence by September 2007. (project details)

  • Work on Phase I of SLR Metaliks' Rs.150 crore three lakh tpa pig iron and billets project at Chikkakasa in Koppal district of Karnataka is likely to commence by September 2007(the project was delay due to unavailability of funds and also awaiting for government clearance). (project details)
  • Civil work for Action Ispat & Power's Rs.75 crore 25 MW coal based power project in Jharsuguda district of Orissa is likely to commence by September 2007. (project details)
  • Civil work for Jaipur Development Authority's indoor stadium project in Jaipur district of Rajasthan is likely to commence by August 2007. (project details)

General developments

  • Around 8 entities including Unitech Group, Bharat Biotech were 0 33643 0 shortlisted for executing the Phase I of Orissa Industrial Infrastructure Development Corporation's biotech-pharma-IT park at Bhubaneswar in Khurda district of Orissa. (project details)
  • ONGC, NTPC to form JV for gas based power projects (more news)
  • Around 30 per cent work on Jarandeshwar SSK's 30 klpd distillery project at Koregaon in Satara district of Maharashtra was completed. (project details)
  • Rico Auto Industries is likely to float an SPV - Uttarakhand Automotive (P) Ltd - for the 35,000 tpa castings project at Sitarganj in Udham Singh Nagar district of Uttaranchal. (project details)
  • NTPC to carry out feasibility study for port-based SEZ (more news)
  • Valeo Electrical Systems in JV for auto plant in Pune (more news)
  • Finalisation of consultant for Pondicherry Special Economic Zone Co's Rs.500 crore special economic zone project at Sedarapet-Karasur in Pondicherry is still under process. The project is still awaiting for environmental clearances from the government. (project details)
  • Around 10 per cent of work on Samiah International Builders' residential complex 'Singapore Residency' at Greater Noida in Gautam Budh Nagar district of Uttar Pradesh is completed. (project details)
  • RIL to take foreign partner for Cauvery asset (more news)
  • GAIL plans CNG distribution in Andhra Pradesh (more news)
  • RGPPL to start power generation by mid-August (more news)
  • NALCO scouting partners for cement plant (more news)

  • India, Japan to sign MoU for freight corridor by August (more news)
  • Around 10 per cent of work on Samiah International Builders' residential township 'NRI Lake City' at Rudrapur in Udham Singh Nagar District of Uttaranchal is completed. (project details)
  • The foundation stone for Public Works Department, Karnataka's airport project in Hassan district of Karnataka is likely to be laid on 31 July 2007. (project details)
  • Himachal Pradesh finalises four hydel projects (more news)
  • BEML emerges lowest bidder for DMRC (more news)
  • TPC, REL plan stake in power exchanges (more news)
  • Maharashtra to adopt PPP model for seven airports (more news)
  • ONGC to take over Transmeridian (more news)
  • Suzlon to shift projects from Maharashtra (more news)
  • Civil work for Sterling's Mac Hotels' Rs.48 crore 5-star business hotel at Kodihalli in Bangalore district of Karnataka is completed. (project details)
  • Around 5 per cent of civil work of Vidarbha Power's Rs.320 crore 2x40 MW captive power project at Ghugus in Wardha district of Maharashtra is completed. (project details)
  • Foundation work for Biomass Energy for Rural India Project's 250 KW biomass power project at Seebinayana Palya in Tumkur district of Karnataka is completed. PPA is yet to be signed with Bangalore Electricity Supply Company. (project details)
  • On 25 June 2007, JSW Infrastructure & Logistics signed letter of intent (LoI) with SEW Constructions for general, civil and architectural works for 4x300 MW coal based power project at Jaigad in Ratnagiri district of Maharashtra. (project details)
  • On 25 June 2007, Indore Municipal Corporation signed letter of intent (LoI) with SEW Constructions for design, construction of 2.7 m internal diameter, 465m, 640m and 1860m (total 2.965 KM) long tunnels for conveyance of clear water for Indore water scheme-Package No.IND/WS/20. (project details)
  • On 11 July 2007, Shree Maheshwar Hydel Power Corporation signed letter of intent (LoI) with SEW Constructions for supply, fabrication and erection of crest gates for the Rs.2,233 crore Maheshwar hydel power project in West Nimar district of Madhya Pradesh. (project details)
  • Cairn hires new rig for Cambay asset (more news)
  • Foundation work for Biomass Energy for Rural India Project's 250 KW biomass power project at Boregunte in Tumkur district of Karnataka is completed. PPA is yet to be signed with Bangalore Electricity Supply Company. (project details)
  • IOC, IBP retail merger by early-August (more news)
  • Around 75 per cent of machinery installation for Gujarat Ambuja Exports' Rs.90 crore 600 tpd maize processing unit in Uttaranchal is completed. (project details)
  • Aras Marketing Corporation's is still awaiting allotment of land for the electrical steel lamination unit at Nelamangala in Bangalore district of Karnataka. (project details)
  • Around 20 per cent work on Srinivasa Shipping & Property Development's IT park 'Metric Tower' at Perungudi in Chennai is completed. (project details)
  • Sasan project to meet its fate on Monday (more news)
  • Chhattisgarh Electricity Company acquired land for setting up a 6 lakh tpa sponge iron unit at Govindpur in Ranchi district of Jharkhand. (project details)
  • Around 90 per cent of civil work on Phase II of TCG Developments India's Rs.180 crore Bengal Intelligent park at Salt Lake in Kolkata district of West Bengal is completed. (project details)
  • MIAL to ink contract with HDIL for rehabilitation of airport land (more news)

Completion of projects (Actual)

  • On 20 July 2007, Union Minister of Commerce & Industry Mr. Kamal Nath inaugurated the auto cluster unit at Pimpri-Chinchwad industrial area in Pune. (project details)
  • Manganese Ore commissioned manganese ore beneficiation plant with a capacity of 5,00,000 tpa at Balaghat mine in Balaghat district of Madhya Pradesh. (project details)
  • Charbhuja Trading & Agencies 500 tpm edible oils project at Hingna in Nagpur district of Maharashtra stands completed. (project details)
  • Work on first unit of Narmada Hydroelectric Development Corporation's Rs.2,145 crore 8x65 MW Omkaraeshwar hydel power project at Mandhata in East Nimar district of Madhya Pradesh was completed. The entire project is scheduled for completion by December 2007. (project details)

Completion of projects (Envisaged)

  • Work on Phase I of Samsung India Electronics' Rs.166 crore special economic zone at Sriperumbudur in Tamil Nadu is scheduled for completion by early-August 2007. (project details)
  • Ess Dee Aluminium is expected to complete expansion of aluminium foil rolling capacity from 3,600 tpa to 18,000 tpa at Daman by September 2007. (project details)
  • Around 60 per cent work on Shreegopal Concrete's 500 tpd cement plant at Dhasla in Bardhaman district of West Bengal iscompleted and full completion expected by October 2007. (project details)
  • Work on 17.5 MW captive power plant, part of Mangalam Cement's Rs.74.50 crore cement expansion project at Morak in Kota district of Rajasthan is underway with completion scheduled for August 2007. (project details)
  • Work upto three floors on two buildings of Jolly Board's IT park at Kanjurmarg in Mumbai is completed. Work on remaining 2 buildings is likely to commence by December 2007. (project details)
  • Around 80 per cent work on Unit I (300 MW) of Haryana Power Generation Corporation's Yamunanagar power project (Stage II) is completed and scheduled for completion by November 2007. Work on Unit II is scheduled for completion by February 2008.(project details)
  • Haryana Power Generation Corporation's 2x600 MW coal based power project in Hisar district is scheduled for completion by 2009. (project details)
  • Work on Soni Auto & Allied industries' automobile ancillaries project at Jamshedpur in Purbi Singhbhum district of Jharkhand is underway with completion scheduled for February 2008. (project details)

Organic Indian Investment Abroad

  • ONGC Videsh to get first oil,gas asset in Kazakhstan (more news)
  • Bharat Forge plans second unit in China (more news)

General Investment Plans

  • Cummins India to invest Rs.250 crore in Pune (more news)
  • Ispat Industries to invest Rs.2,100 crore by 2009 (more news)
  • JK Paper to invest Rs.700 crore by 2010 (more news)
  • CESC chalks out plans for various projects (more news)
  • General Electric to invest $8 billion for infrastructure projects (more news)
  • SRMB Udyog to foray into retail sector (more news)
  • BPCL to invest Rs.1,500 crore in exploration, production projects (more news)
  • DLF to invest Rs.6,000 crore by 2010 (more news)

Project Financing

  • AAI plans ECB route to upgrade airports (more news)

Minor & old orders

  • N.K. Group, UAE has been awarded the contract for development of Kerala Industrial Infrastructure Development Corporation's knowledge park at Puzhakkalpadam in Thrissur district of Kerala. (project details)
  • Madhya Pradesh Road Development Corporation awarded contract to K T Developers, Indore to implement the Rs.56.33 crore 100 km road between Chandrapur-Alirajpur-Kukshi-Badwani in Jhabua, Dhar and Barwani district of Madhya Pradesh on BOT basis. (project details)

Overseas Orders

  • Dayim Punj Lloyd bags EPC contract (more news)

Click here to view all tenders and EOIs floated during the period 22 - 28 July 2007.

To view the Weekly Round-Up for the period 15 - 21 July 2007, click here

ProjectsToday Weekly Round Up: Archives

 

PJWRUP
← All latest storiesBack to top →