ProjectsToday Weekly Round Up: 14-20 August 2005Illustrative image – not actual.

Every Saturday, ProjectsToday brings together important project-related developments transpiring during the week, in the Weekly Round-Up. These developments are presented as information nuggets with relevant hyperlinks leading you to more details available in the sections -- Project News, Projects Information and Project Tenders. The entire compilation has been organized in subjects to facilitate reference. The following report pertains to the period 14 August 2005 to 20 August 2005.

New Projects
(List is not exhaustive, for full list of projects added, please use Advanced Search of Projects Information Section)

  • Greenply to set up plywood unit in Uttaranchal (more news)
  • KK Birla Group plans greenfield sugar unit (more news)
  • Govt moots coastal power plants (more news)
  • Shyam Steel announces Rs.550 crore expansion (more news)
  • VS Dempo setting up 1 mln tpa steel project (more news)

Financial closure

  • Krishna Priya Power's Rs.20 crore Lower Sileru Mini Hydel Power project in Khammam district of Andhra Pradesh is in the process of achieving financial closure with completion scheduled for August 2006. (project details)

Response to tenders

Approvals, Clearances

  • NINL's IPO gets in-principle government nod (more news)

MoUs signed

  •  Salem Group and West Bengal government sign MoU (more news)

 Expected commencement of work

  • The Rs.1,125 crore Pathadi Thermal power project's construction work at Pathadi in Korba district of Chhattisgarh is expected to begin soon; which bhoomi pujan was scheduled in mid-August 2005. The project is being implemented by Lanco Amarkantak Power. (project details)

 Project impediments

  • The Central Electricity Regulatory Commission rejected PGCIL's petition seeking to revise upwards the project cost from Rs.617 crore to 686.32 crore of the proposed Bina-Nagda-Dehgam Transmission Line project of Power Grid Corporation of India in Ujjain and Sagar district of Madhya Pradesh and Gandhinagar district of Gujarat. (project details)

Other developments

  • Unity Infraprojects is appointed as civil contractor for executing Government of Assam's Rs.75.20 crore Secretariat Complex at Dispur in Kamrup district . (project details)
  •  The Board of Directors of Monnet Ispat decided to raise the capacity of its Rs.225 crore captive power plant project at the new site of Raigarh to 90 MW from 75 MW. (project details)
  •  The Union Ministry has asked Indian Oil Corporation to appoint financial consultants by 31 August 2005 for the India-Iran pipeline project of GAIL. (more news, project details)
  • ITC shortlisted three states-- Andhra Pradesh, Gujarat and Maharashtra-- for setting up its Rs.2,500 crore ECF paper project. The final decision regarding the exact location was expected in September 2005. (more news, project details)
  • Government targets $5 billion FDI in FY06 (more news)
  • Prime Minister's Independence Day address: Highlights (more news)

Completion of projects

  • It was learnt that Colgate-Palmolive's Rs.50 crore Toothpaste project Baddi in Solan district of Himachal Pradesh is completed and started commercial production. (project details)
  •  It was learnt that on 16 August 2005, the Honourable President of India, Dr.A P J Abdul Kalam inaugurated the Rs.40 crore drug research center of Ranbaxy Laboratories' at Gurgaon district of Haryana. (project details)
  • Work on Rs.250 crore, commercial cum parking complex 'Eros Corporate Towers' of Nehru Place Hotel was completed on 8 August 2005. (project details)
  •  Garden Silk Mills' Polyester Yarn (Jolwa) expansion project in Surat district of Gujarat was completed and and commercial production started on 15 August 2005. (project details)

 Envisaged completion of projects

  • Maharashtra Industrial Development Corporation's Rs.100 crore Thane-Belapur Road Upgradation project in Thane district of Maharashtra is scheduled for completion by March 2007. (project details)
  • Work on Phase-I of the Mawana Sugars' Rs.80 crore sugar project at Nanglamal in Meerut district of Uttar Pradesh is scheduled for completion by November 2005. (project details)
  • Bharat Aluminium Corporation's Rs.4000 crore aluminium smelter and captive power project in Korba district of Chhattisgarh completed construction of 216 pots out of total of 288 and 50 pots were commissioned. The second power unit is expected to be commissioned in August 2005 and the entire project was scheduled to be operational by March 2006. (project details)
  •  Work on spinning mill project of Cimmco Spinners at Chincholi in Solapur district of Maharashtra is scheduled for completion by September 2005. (project details)
  • Work on the Phase I of software development centre at Siruseri IT Park in Chennai was completed on May 2005 with Phase II scheduled for completion by September 2006. The Rs.60 crore project is implemented by Patni Computer Systems. (project details)
  • Work on Phase I of Software Development Centre at Airoli near Navi Mumbai in Thane district is expected to be completed within 2 months and work on phase II scheduled for completion by March 2006. The Rs.230 crore project is implemented by Patni Computer Systems. (project details)
  •  Phillips Carbon Black's Rs.120 crore captive power project of 30 MW at Durgapur in Bardhaman district of West Bengal is scheduled for completion by March 2007. (project details)
  •  J K Paper's Rs.235 crore duplication board papers project at Central Pulp Mill near Songad in Surat district of Gujarat is scheduled for completion by February 2007.(project details)
  • Work on Bangalore Mahanagara Palike's Rs.16.98 crore flyover project at National College Circle in Basavanagudi is nearing completion and is expected to be ready by August 2005. (project details)
  • Numaligarh Refinery's Rs.296.86 crores motor spirit project at Numaligarh in Golaghat district of Assam is scheduled for completion by March 2006. (project details)
  • The Rs.11 crore catheter facility of Relisys Medical Devices in Hyderabad district of Andhra Pradesh is expected to undergo trial runs by January 2006. (project details)
  • Uttar Pradesh Power Corporation's Vishnuprayag-Muzaffarnagar Transmission line Chamoli district of Uttaranchal and Muzaffarnagar district of Uttar Pradesh is underway with completion scheduled for March 2006. (project details)
  • Ind-Swift Laboratories' Rs.25 crore R & D center at Mohali in Rupnagar (Ropar) district of Punjab is scheduled for completion by September 2005. (project details)
  • Work on Rs.1,100 crore cement project of Jaiprakash Associates at Solan district of Himachal Pradesh is scheduled for completion by March 2007. (project details)
  • Bangalore Mahanagara Palike's Rs.14.60 crore grade separator project at Rajajinagar in Bangalore district of Karnataka is nearing completion and will be ready for public use from September 2005. (project details)
  • Ramco Industries' 72,000 tpa, fibre cement sheets project in Kachchh district of Gujarat is scheduled for completion by December 2005. (project details)
  • Work on Phase-I of Bangalore-Mysore Corridor Road project implemented by Nandi Infrastructure Corridor Enterprises is scheduled for part completion by September 2005. (more news, project details )
  • Work on the 3.5 MW, co-generation power project of Oswal Woollen Mills at Shedpur in Punjab is scheduled for completion by October 2005. (project details)

Revival of projects

  •  Dabhol power project: Gail confident of sourcing LNG soon (more news)

Minor tender for ongoing mega project

  • BHEL has invited bids for erection, testing and commissioning of electrical control and instrumentation work for GTG and HRSG and connected work for units 5 & 6 of 2x25 MW co-generation plant in Visakhapatnam district of Andhra Pradesh. (tender details)

 Organic Indian Investment Abroad

  • NTPC, REL plans power projects abroad (more news)
  • Tata Steel eyeing South-East Asia for second acquisition (more news)

Long-term Investment Plans

  •  Bharti to invest Rs.120 crore in western region (more news)
  • India eyes $1 billion WB aid for Bharat Nirman (more news)

Project Financing

  •  Ind-Swift Laboratories raised $10.6 million through the issue of 25 lakh global depository receipts for its Rs.12.15 crore bulk drugs expansion project at Derabassi in Patiala district of Punjab. (project details)
  • Duncans Goenka group had decided to privately place 15 lakh convertible warrants at Rs.97 a piece aggregating to Rs.14.6 crore and the proceeds will be used to finance the Stone India's, a Duncans Goenka group company, for the air dryers project at Baddi in Solan district of Himachal Pradesh. (project details)