ProjectsToday Weekly Round Up: 07 - 13 January 2007Illustrative image – not actual.

Every Saturday, ProjectsToday brings together important project-related developments transpiring during the week, in the Weekly Round-Up. These developments are presented as information nuggets with relevant hyperlinks leading you to more details available in the sections -- Project News, Projects Information and Project Tenders. The entire compilation has been organized in subjects to facilitate reference. The following report pertains to the period  07 - 13 Jan 2007.

New Projects
(To view new projects added during the period 06 - 13 Jan 2007, click here)

Financial closure 

Response to tenders 

  • ONGC shorlist Indian companies for offshore support vessels (more news)

Approvals, Clearances 

  • On 9 January 2007, Coastal Gujarat Power's 4,000 MW Mundra ultra mega power project received clearance from the Ministry of Environment & Forest (MoEF). (project details)
  • Six more JNNURM projects worth Rs.352.83 crore approved (more news)
  • Maharashtra approves 2,000 MW fresh power capacity (more news)
  • Approval received for Kandla Port's four cargo berths (more news)
  • Rama Newsprint board approves Rs.630 crore expansion plan (more news)
  • On 22 December 2006, the Ministry of Environment & Forests cleared Bhagiradha Chemicals & Industries' Rs.18.30 crore 2,250 tpa pesticides expansion project in Prakasam district of Andhra Pradesh. (project details)

MoUs signed 

  • III signs MoU with Gujarat for 2,000 km highways (more news)

Foundation stone laying 

  • On 9 January 2006, Union power minister, Mr. Sushilkumar Shinde laid the foundation stone for Rajasthan Rajya Vidyut Utpadan Nigam's Rs.750 crore 250 MW Suratgarh power project in Ganganagar district. (project details) 

Commencement of work (Actual)

  • Harinagar Sugar Mills' Rs.40 crore 1,500 tccpd sugar expansion project at Harinagar in Paschimi Champaran district of Bihar was completed. (project details)
  • Samriddhi Ispat's 40,000 tpa rolled steel products project at Chandwara in Kodarma district of Jharkhand was completed. (project details)

Commencement of work (Envisaged)

  • Fab City Project: Phase II to begin by April 2007 (more news)
  • Land acquisition process for K M Sugar Mills' Rs.150 crore 5,000 tccpd sugar project in Bihar is underway. Work on the project is expected to commence by March 2007 with completion scheduled by November 2007. (project details) 
  • Work on Fuelco Washeries' Rs.800 crore 2 million tpa coal washery project at Belsani in Chandrapur district of Maharashtra is expected to commence by January 2007. (project details)
  • Work on Dollon's Food Products' Rs.5 crore milk processing expansion project at Dhalabhagan in Hooghly district of West Bengal is expected to commence by early-February 2007 with completion scheduled for April 2007. (project details)
  • Work on Damodar Valley Corporation's Rs.3.70 crore hospital project at Chandrapura in Bokaro district of Jharkhand is likely to commence by February 2007 with completion scheduled by early 2009. (project details) 

Project impediments 

  • Jodhamal Foods' Rs.6.16 crore food processing complex at Kasauli in Solan district of Himachal Pradesh is put on hold due to delay in approvals from the state government and is re-scheduled to commence by March 2007. Work on Phase I and II is scheduled for completion by September 2007 and December 2007 respectively. (project details)

General developments 

  • BPCL buys stake in three overseas blocks (more news)
  • The company has shortlisted three consultants - Avante Garde, Mitcon and one Delhi-based company (not disclosed) for Kamlapur Sugar & Industries' 3,500 tccpd sugar expansion project in Lucknow district of Uttar Pradesh. Civil works is likely to commence by April 2007. (project details)
  • Tamil Nadu Road Development Authority is in the process of submitting a revised detailed feasibility report on Chennai Metropolitan Development Authority's Rs.480 crore outer ring road project to CMDA. Land acquisition for the Phase I [from Vandalur to Nadukuttagai (29.5 km)] is completed and for Phase II [till Minjur on TPP Road] it is expected to complete by December 2007. (project details) 
  • Hardy Oil strikes oil & gas in Cauvery basin (more news)
  • ONGC surrenders four blocks in NELP I, II (more news)
  • Indraprastha and Apollo Hospital from Delhi is shortlisted for the Rs.10.62 crore hostel building project at Vishnupuri in Nanded district of Maharashtra. (project details)  
  • Jharkhand UMPP to be awarded by July 2007 (more news)
  • Power Purchase Agreement for Bhushan Energy's Rs.8,483 crore 2,000 MW coal based power project in Angul district of Orissa is signed. Work on Phase I is scheduled for completion by January 2010 and Phase II by January 2011. (project details)  
  • The detailed project report for Vishal Exports Overseas' Rs.22 crore 2x2.8 MW Nandakini - III hydro power project in Chamoli district of Uttaranchal is likely by end-June 2007. The geographical studies and the discharge measurement work for the project is underway. (project details) 
  • Sinosteel to sign agreement for steel plant in Orissa (more news)
  • The EPC contractor for OPG Power Generation's Rs.310 crore 77 MW coal based power unit at Gummidipoondi in Thiruvarur district of Tamil Nadu will be finalised by February 2007. The earlier EPC contractor - Shriram EPC for the project is cancelled (reasons were not disclosed for the cancellation). (project details) 
  • JNPT is in the talks with consultants to float the final tender for Jawaharlal Nehru Port Trust's Rs.3,500 crore IV container and marine chemical terminal project at Nhava Sheva in Raigarh district of Maharashtra by March 2007. (project details) 
  • Oilex eyeing stakes in three oilfields (more news)
  • Ritesh Industries in JV with API for real estate project (more news)
  • Gateway signs pact with Punjab Conware for freight station (more news)
  • Around 50 per cent work on 22 MW petcoke based power plant (part of Rs.218 crore 0.5 million tpa cement expansion project) at Nimbahera in Chittaurgarh district of Rajasthan is completed. (project details) 
  • Land acquisition process for Nitin Cylinders' Rs.118 crore seamless cylinders project in Visakhapatnam district of Andhra Pradesh is complete and the company has commenced civil construction for the Phase I of the project. Commercial production for the first & second phase is likely by April 2007 & October 2007 respectively. (project details) 
  • ONGC receives 22 bids for marginal on-land fields (more news)
  • Srinivasa Construction and J Balaramji Constructions of Nagpur in joint venture is likely to bag the contract for Government of Maharashtra's Rs.125.75 crore Paghora lift irrigation project. (project details) 
  • AMR, Malaysian investor float coal mining JV in Indonesia (more news)
  • Government to offer more on-land blocks under NELP VII (more news)
  • IOC, RIL plans JV for natural gas retail (more news)
  • Land acquisition process for Century Textiles & Industries' Rs.790 crore 2 million tpa cement project at Gadchandur in Chandrapur district of Maharashtra is underway. Work on the project is expected to commence by April 2007. (project details) 
  • Petroleum ministry rejects ONGC's tie-up plans with BG, BP (more news)
  • On 11 January 2007, the bidders conference for Rs.4,200 crore power transmission projects in India was inaugurated by Union minister of Power, Mr.Sushilkumar Shinde. (project details) 

Completion of projects (Actual)

  • On 12 January 2007, Finance Minister, Mr. P Chidambaram dedicated to the nation Indian Oil Corporation's Rs.4,165 crore 12 million tpa Panipat expansion project in Haryana. (project details) 
  • Binayak Imaging & Diagnostic's multi specialty hospital project 'Binayak Healthworld' at Kolkata in West Bengal is likely to be inaugurated on 17 January 2007. (project details) 
  • Fiem Industries' Rs.40 crore automobile ancillaries project at Nalagarh in Solan district of Himachal Pradesh began commercial production. (project details) 

Completion of projects (Envisaged)

  • Work on Milgram Milk Specialities' Rs.100 crore dairy farm complex at Vandiperiyar in Idukki district of Kerala is scheduled for completion by January 2009. (project details) 
  • Work on Cresent Power's Rs.185.58 crore 2x20 MW Asansol power project in Bardhaman district of West Bengal is scheduled for completion by 2009. (project details) 
  • Civil work for Vasant Spinners' Rs.50 crore 26,400 spindles cotton yarn project at Thimmapuram in Guntur district of Andhra Pradesh is completed. Commercial production is expected by February 2007. (project details)  
  • Civil work for Veecon-IPA Gastechnik's Rs.26.06 crore 4.8 MW Jagat Sukh small hydroelectric power project in Kullu district of Himachal Pradesh is completed. Commercial production is expected to begin by March 2007. (project details)  
  • Work on Mumbai Corporation of Greater Mumbai's Rs.27.90 crore pedestrian subway project near Metro Cinema in Mumbai is scheduled for completion by June 2007. (project details)
  • Deendayal Magasvargiya Sahakari Soot Girni's Rs.15 crore 11,000 spindles cotton yarn expansion project at Kameri in Sangli district of Maharashtra is scheduled for completion by December 2007. (project details) 
  • Around 70 per cent work on Sri Vinayaka Spinning Mills' Rs.18 crore 5,000 spindles viscose staple fibre project in Namakkal district of Tamil Nadu is completed. Full completion is expected by April 2007. (project details) 
  • Around 30 per cent work of Dukes Consumer Care 500 tpa confectionery expansion project in Hyderabad district of Andhra Pradesh is completed. The project is scheduled for completion by June 2007. (project details)
  • Work on Electrotherm India's 30 MW waste heat based power unit (a part of Rs.520 crore integrated steel project) in Kachchh district of Gujarat is scheduled for completion by July 2007. Work on pig iron unit and rolling mill and TMT bars unit is expected to commence by January 2007 and March 2007 respectively. (project details) 
  • Work on Jeypore Sugar Co's 5,000 tccpd sugar unit at Pothavaram in West Godavari district of Andhra Pradesh is scheduled for completion by December 2007. Work on 16.8 MW power unit is expected to commence by April 2007. (project details) 
  • Civil work for Chhatrapati SSK's Rs.38 crore 1,250 tccpd sugar project at Majalgaon in Bid district of Maharashtra is completed. Commercial production is expected to begin by March 2007. (project details)
  • Around 60 per cent work on Phase I of Jain Sponge's Rs.250 crore integrated steel project at Durlaga in Jharsuguda district of Orissa is completed. Full completion is expected by March 2007. (project details)
  • Around 90 per cent work on Government of Maharashtra's Rs.1.5 MW Wan hydel power project in Nagpur district of Maharashtra is complete. Full completion is expected by end January 2007. (project details)

General Investment Plans

  • SAIL to invest Rs.1 lakh crore for capacity expansion (more news)
  • Aeren plans Rs.1,500 crore infrastructure projects (more news)
  • Aditya Birla Group to invest Rs.15 bn in Gujarat (more news)
  • Dubai World to invest Rs.2,600 crore in Kulpi port, SEZ (more news)

Click here to view all tenders and EOIs floated during the period 07 - 13 Jan 2007.

To view the Weekly Round-Up for the period 31 Dec 2006 - 06 Jan 2007, click here

ProjectsToday Weekly Round Up: Archives

PJWRUP
← All latest storiesBack to top →