Illustrative image – not actual.Bhutan has undertaken a project to reconstruct 5 old
bridges along major national highways in the country. The project, which has
received Japanese funding, is estimated to cost US$ 13 million. Work on the
project, which began in August 2001, is on schedule and would be completed in
2004, according to the department of roads (DoR).
The Kurizampa bridge in Mongar dzongkhag, which was
taken up first, would be opened to traffic by mid October, 2002.
Work on the Chamkharzam bridge in Bumthang is about
70 per cent complete. The completed works include the foundation and erection
of the superstructure. The laying of concrete slabs over the bridge, asphalt
pavement work and connecting the 2 ends of the bridge to the road is yet to be
undertaken. This bridge is expected to be ready by the end of October, 2002.
Work on another bridge the Mangdezam in Zhemgang
would start in August 2002, while preparatory works have already begun on the
Waheyzam in Wangduephodrang and the Bjeezam in Trongsa.
The project is being implemented on a turnkey basis with DNC as the contractors and Docon Co Ltd providing the supervisory consultancy services on behalf of the DoR.
It may be mentioned that the superstructures of the 5
bridges are being prefabricated in Japan and shipped to Bhutan via Kolkata,
India.
Four of the 5 bridges being reconstructed all along
the lateral east-west highway that connects Thimphu to Trashigang in the east.
This project is expected to increase the loading capacity of the bridge.