Production delayed for MMG Textiles cotton unitIllustrative image – not actual.
The Projects Today research team has learnt that commercial production at the MMG Textiles’ cotton yarn unit has further delayed on account of financial issues.

Out of the total cost of Rs 80 crore, 75 percent of the cost was funded by bank and the balance was met from internal accruals.

The cotton yarn unit with a capacity of 24,480 spindles, spread over four acre of land, is located at Metro Textile Park, Kagal Five Star MIDC, in Kolhapur district of Maharashtra.

As per the information gathered by Projects Today, the promoter was to acquire the required land for the textile unit by mid-July 2014. However, even after receiving necessary approvals and clearances, land could not be acquired.

According to recent updates with Projects Today, the project execution has been postponed due to financial issues. The promoter anticipates to commence work by July 2019.

V N Kane of Ichalkaranji is in-charge as the consultant, and Lakshmi Machine Works is the plant and machinery supplier.