Prime Minister’s Office sets 2020 deadline for Nagaland rail projectIllustrative image – not actual.

The Prime Minister’s Office (PMO) has set 2020 as the deadline for completion of 83 km rail link between Dhansiri in Assam and Zubza in Nagaland.

The rail project which involves construction of around 190 bridges and almost 26 km of tunnels has been delayed for the past 11 years. It has seen a cost estimate rise from Rs 850 crore to Rs 3,000 crore. The project will be completed in three phases.

Progress of the Dhansiri-Zubza project has been stuck due to land acquisition issues involving 1.55 km in Assam. This has affected the progress of Phase-I of the project - from Dhansiri to Sukhovi stretching 16 km. Phase-I of the project is scheduled to be completed by December 2018.

The PMO has asked the Assam government to acquire the required land by 15 December 2017. Also, the Nagaland government has been directed to acquire and hand over the 24 km land for the project by 15 February 2018.

 