Prime Minister, Vice President’s residences to be ready by 2022 under Central Vista projectIllustrative image – not actual.
The Vice President of India and Prime Minister’s new residence under the Central Vista project are scheduled to be completed by May and December 2022 respectively, as per the Central Public Works Department (CPWD), as the Environment Ministry’s expert appraisal committee (EAC) has granted the necessary clearance for the rest of the buildings under the plan. 
 
The project also includes a Common Central Secretariat and the Special Protection Group (SPG) building. 
 
As per CPWD’s submission to the Ministry, the work on Parliament is scheduled to be completed by November 2022, the Vice President of India enclave by May 2022, and the Prime Minister’s residence and the SPG building by December 2022. 
 
The cost of the project, which also includes a Common Central Secretariat, has been pegged at Rs 13,450 crore. The plan, being handled by the Union Ministry of Housing and Urban Affairs, involves a new Parliament building by 75th Independence Day in 2022. 
 
The entire project, which includes constructing 11 administrative buildings to house all the government ministries, is slated to be finished by 2024. Tata Projects was awarded the contract for construction of the new Parliament complex on 29 September 2020.
 
In December 2020, EAC conditionally approved new terms of reference (ToR) for the development or redevelopment of Common Central Secretariat Buildings, a central conference centre, the Prime Minister’s Residence, the Vice-President’s enclave and a building for the Special Protection Group (SPG).
 
Under the project, the Prime Minister’s residence will be shifted behind the existing South Block complex while the residence of the Vice President is proposed to be relocated behind North Block. 
 
The plan also includes razing buildings, including Shastri Bhawan, Udyog Bhawan and Krishi Bhawan that house government ministries to build a Common Secretariat for around 70,000 Central government employees who are currently located across 30 buildings. 
 
As proposed, around 4,918 trees have to be maintained within the project site during the operation phase of the project. The landscape planning would include plantation of native species. The existing trees will be counted for this purpose.
 
Also, there should be two continuous online Ambient Air Quality Monitoring stations in the project area before the start of demolition work. Moreover, at least 50 anti-smog guns and 15 anti-smog towers will be provided to curb air pollution during construction phase, and 15 anti-smog towers will be installed during operation phase.

 