Illustrative image – not actual.Karnataka Power Corporation has decided to go ahead with the price bids for fuel supply to the 1,400 MW Bidadi gas station.
The price bids would be opened in the second half of October. At present, there are three qualified bidders for the project -- the ONGC-Petronet combine, the IOC-Petronas of Malaysia combine and Reliance Industries.
The bid conditions were modified in the line with the demands made by some of the bidders. The timeframe prescribed is between 36 months and 48 months from the date of award of contract. The fuel supply contract is for a period of 15 years with a grace period of another two years.
The Bidadi station is expected to require at least 1.4 million tonnes of gas per year, assuming a plant load factor of 85 per cent. This translates into about 73 million British thermal units (51.81 MMBTU = one tonne).