Premature awarding of highway projects leading to delays: Planning CommissionIllustrative image – not actual.

According to the Planning Commission, contracts awarded under NHDP-II, before land acquisition, National Highways Authority of India is causing huge delays, besides escalating project costs by more than Rs.16,000 crore.

Since NHDP-II is being implemented largely through construction contracts funded out of budgetary support based on the cess revenues, it will crowd out other more important highway projects unless steps are taken to control costs, the  commission feels. Against a target of 5,722 km to be contracted in 2005-06, the actual achievement has been only 4,164 km, or 73 percent.

The commission also said only 22 per cent of the required land for the north-south and east-west corridors had been physically acquired, while notifications have been issued for 48 per cent of the requirement assessed so far. An independent critical assessment will be made on each of these projects to identify the problem areas. Based on this, a realistic completion date will be set and the NHAI will take responsibility for meeting it.

← All latest storiesBack to top →