Preliminary works related to the construction of four six-lane flyovers at IT Park, Musakhedi, Satyasai Square and Niranjanpur Square in Indore, Madhya Pradesh have begun.
This includes clearing of bushes and related works, while service roads for traffic diversion has begun in other places. The initial activities of the flyover will be completed this month, and digging for the pillar will begin. Preparations are underway to start the work at all the four sites before the onset of monsoon.
These flyovers are being developed by the Madhya Pradesh Road Development Corporation (MPRDC) under the Setu Bandhan Scheme of the Central government. Two flyovers will be built on the BRTS corridor, and the remaining two on the Eastern Ring Road at a cost of over Rs 267 crore. The construction will take about one-and-a-half years to complete.
Prior to the construction, the geotechnical survey of the site has been completed, and traffic diversion plan duly submitted to the police administration. The construction work will be done in phases, causing relatively less trouble to the commuters.