Illustrative image – not actual.In a move o shift the Indian Oil Corporation (IOCL) product terminals at Korukkupet and Tondiarpet to Vallur in Tiruvallur district, preliminary works is underway to lay new pipelines from Ennore to the Chennai Petroleum Corporation (CPCL) refinery in Manali, Tamil Nadu.
The total project cost, including laying of pipelines and construction of terminal, will be Rs 730 crore.
The upcoming new terminal will take over functions of Korukkupet, Tondiarpet facilities.
The terminals have been in operation for many decades receive, store and supply fuel, lubricants and oil. The terminal caters to the fuel needs of Chennai, Tiruvallur, Kancheepuram and other neighbouring districts.
The terminal will be shifted following orders from various bodies, including the National Green Tribunal (NGT) and the Petroleum and Explosives Safety Organisations, and taking into consideration the need to be compliant with safety standards of the oil industry.
A total of 102 acre of land parcel has already been procured at Vallur in Minjur in Tiruvallur district for the terminal.
The company has planned to provide dual pipeline connectivity at the Vallur terminal, one from Chennai port and another from Ennore port.
The right of way (RoW) has been obtained for laying pipelines from Ennore to CPCL. The proposal is under consideration of the IOCL Board while the approval for the same is expected in another three to four months.
The project will be completed in 30 months following the commencement of work.
The total project cost, including laying of pipelines and construction of terminal, will be Rs 730 crore.
The upcoming new terminal will take over functions of Korukkupet, Tondiarpet facilities.
The terminals have been in operation for many decades receive, store and supply fuel, lubricants and oil. The terminal caters to the fuel needs of Chennai, Tiruvallur, Kancheepuram and other neighbouring districts.
The terminal will be shifted following orders from various bodies, including the National Green Tribunal (NGT) and the Petroleum and Explosives Safety Organisations, and taking into consideration the need to be compliant with safety standards of the oil industry.
A total of 102 acre of land parcel has already been procured at Vallur in Minjur in Tiruvallur district for the terminal.
The company has planned to provide dual pipeline connectivity at the Vallur terminal, one from Chennai port and another from Ennore port.
The right of way (RoW) has been obtained for laying pipelines from Ennore to CPCL. The proposal is under consideration of the IOCL Board while the approval for the same is expected in another three to four months.
The project will be completed in 30 months following the commencement of work.