Pre-construction activity underway for Hapur Bypass-MoradabadIllustrative image – not actual.
IRB Hapur Moradabad Tollway, the concessionaire, envisages six-laning of Hapur Bypass-Moradabad section with Hapur Bypass from 50.000 km (design ch 50.000 km) to 148.277 km (design ch 149.867 km) of NH-24 (new NH-9) in the state of Uttar Pradesh. The road project is expected to be completed by 2020.

H G Infra Engineering, a subsidiary of IRB Infrastructure Developers, has bagged an order worth Rs 1,172.29 crore from Modern Road Makers for development of the project on engineering, procurement, construction (EPC) basis.

The project will be developed under build operate transfer (BOT-Toll) basis on design, build, finance, operate, and transfer (DBFOT) pattern under NHDP-V. The estimated cost of the project is Rs 2,140.93 crore.

Projects Today has got confirmation that pre-construction activity and mobilisation work was underway on the development. Besides, construction work on the project was likely to commence soon.

The project initiated in 2011 is progressing at a slow pace. The process of acquisition of land delayed the execution of project work. On 2 April 2018, IRB Infrastructure Developers received letter of award (LoA) for the development.

The concession period of the project was 22 years, including construction period of 910 days. The company has also signed concession agreement with the National Highways Authority of India (NHAI) for the period of 264 months for the project. 