Reliance Power has commenced pre-commissioning activities on its 100 MW concentrated solar power (CSP) project in Rajasthan's Jaisalmer district.

 

The concentrated power plant (CSP) project is based on Compact Linear Fresnel Reflection (CLFR) technology.

 

The 100 MW CSP plant, being built at a cost of Rs 2,100 crore, will be adjacent to the 40 MW solar photovoltaic project commissioned by the company last year.

 

The project is set to be commissioned by March 2014. Rajasthan Sun Technique Energy, a wholly owned subsidiary of Reliance Power, was awarded the CSP project in December 2010, based on international competitive bidding conducted by NTPC Vidyut Nigam, a subsidiary of NTPC, under the Jawaharlal Nehru National Solar Mission of the government of India.

 

The project is financed through debt from multilateral agencies like Asian Development Bank (ADB), Export Import Bank of the United States, Financerings Maatschappu Voor Ontwikkelingslanden N.V. (FMO), Netherlands and Axis Bank. 

 