The pre-cast segment casting, which is a pre-curser to the super structure of Bridge Deck Construction, has been completed for Mumbai Trans Harbour Link (MTHL).
The completed 75 tonne segment, with a dimension of 14.8 mtr length x 3.32 mtr width x 3.85 mtr height, will be erected in the marine section at a distance of six km inside the sea.
This is India’s longest water bridge.
The project has also completed two km of Temporary Access Bridge, which includes both sides, 16 pile caps and 10 piers.