Illustrative image – not actual.POWERGRID has successfully commissioned the Transmission Scheme for Solar Energy Zones in Ananthapur and Kurnool districts of Andhra Pradesh, marking a significant milestone in strengthening India’s renewable energy evacuation infrastructure.
The project is designed to support the transmission of 2,500 MW solar capacity from Ananthapur and 1,000 MW from Kurnool, and became fully operational on 24 June, 2026. The notification for commercial operation (DOCO) was issued on June 25 and received by POWERGRID on 26 June, 2026. The transmission project was initially executed under POWERGRID Ananthpuram Kurnool Transmission, a wholly owned subsidiary of Power Grid Corporation of India. However, following a corporate restructuring exercise, the entity was merged with POWERGRID Khawda II-C Transmission effective 01 March, 2026, as per an order from the Ministry of Corporate Affairs.
The commissioning of this transmission corridor is expected to significantly enhance grid connectivity and enable efficient evacuation of renewable power generated from large solar parks in the region. It also supports India’s broader clean energy transition goals by improving infrastructure readiness for large-scale solar integration and ensuring stable power transmission from renewable-rich zones to demand centres across the national grid.