Illustrative image – not actual.The Union government has approved a Rs 4,754 crore power transmission scheme for Arunachal Pradesh and Sikkim.
The scheme was approved by the Cabinet Committee on Economic Affairs. The projects will be implemented by Power Grid Corporation with its consultancy fee of 12 per cent of the execution cost. After commissioning, the power transmission projects will be owned and maintained by state governments.
The Ministry of Development of Northeastern Region (DONER) had conveyed its inability to finance the project due to budgetary constraints. The project will now be taken up through a central sector scheme under the Ministry of Power.
The project is to be implemented within 48 months from the first fund release to Power Grid Corporation.
The intra-state transmission and distribution systems in the north eastern states are very weak. Presently, only five out of 20 districts in Arunachal Pradesh are connected to the transmission network.