The Power Secretary, Mr R V Shahi, reportedly criticized power PSUs for their inability in spending funds allocated to them towards the capacity addition programme.

The Secretary has also expressed fears that the targeted capacity addition of 41,000 MW for the Tenth Plan period (2002-07) might fall considerably short of target. During 2002-03, of the targeted 4,087 MW, only 2,858 MW was commissioned.

The fund allocations to NHPC have been considerably enhanced to Rs.14,000 crore for the Tenth Plan period, as against Rs.4,000 crore in the preceding Plan period.

The break-up of the 41,000 MW targeted for the ongoing Plan period is:

  Capacity (MW)
2002-03* 2,858
2003-04 5,202
2004-05 7,677
2005-06 8,218
2006-07 17,155
Total (Approx) 41,000
*Actual addition, against target of 4087 MW