The Union Ministry of Power has cut down its 12th plan capacity addition target.
The capacity addition target has been scaled down from over 1 lakh MW to 75,785 MW. The 12th plan target is less than the ministry’s goal for the 11th plan (78,700 MW).In October 2011, a working group on power for the 12th plan submitted its report to the Planning Commission. The decision has come in the wake of huge shortage of coal and gas in the country.
India aims to grow at 9 per cent per annum in the 12th plan and its current peak demand deficit stands at 10.3 per cent with an installed capacity of 1,82,344 MW. For the country to become power surplus, there is need to add at least 1 lakh MW during the 12th plan. For the last two years, coal mining projects with reserves of over 600 million tonne have been stuck in the “no-go” category, leading to reduced production from CIL. The production of gas from Reliance Industries’ KG basin has also been on the decline. As a result, many planned gas based projects are stalled.