Power Ministry transfers Srinagar-Leh Transmission System to PGCILIllustrative image – not actual.
The Ministry of Power, government of India, has transferred 220 kV Srinagar-Drass-Kargil-Khaltsi-Leh Transmission System to the Power Grid Corporation of India (PGCIL), a Maharatna CPSU of the government of India. 
 
The transmission system was dedicated to the nation by Prime Minister Narendra Modi in February 2019, and it connects the Ladakh region to the national grid, ensuring quality and reliable power supply.
 
Built at a height of around 3,000-4,000 mtr, this 335 km long transmission line traverses snow-bound difficult hilly terrain. It comprises four new state-of-the-art 220/66 kV gas insulated sub-stations and 66 kV interconnection systems at Drass, Kargil, Khaltsi and Leh.
 
The project was executed by PGCIL on consultancy basis under Prime Minister’s Reconstruction Plan (PMRP) Scheme.
 
Subsequent to reorganisation of the erstwhile state of Jammu & Kashmir into the Union Territories of Jammu & Kashmir and Ladakh, the 220 kV Srinagar-Leh Transmission System has been re-designated as Inter State Transmission System (ISTS) and transferred to PGCIL with effect from 31 October 2019, the date of formation of the two Union Territories. 
 