Illustrative image – not actual.The Union Ministry of Power has sought an outlay of Rs.25,000 crore for the 10th Five Year Plan, to support the Rs.50,000 crore Accelerated Power Development Programme (APDP), which is aimed at promoting distribution reforms and improving the financial health of the state electricity boards in the country.
Presently, the power ministry is funding 63
distribution circles under APDP scheme. The remaining identified 350
distribution circles are expected to be covered during the 10th Plan
for which around Rs.50,000 crore is required. The estimated investment in each
distribution circle is around Rs.80 – Rs.100 crore.
According to reports, the required Rs.50,000 crore
would be funded through a combination of grant and loan in the ratio of 90:10
for special category states and in the ratio of 50:50 for all other states. The
loan component will be provided by agencies such as the Power Finance
Corporation and the Rural Electrification Corporation. It is on this basis that
an outlay of Rs.25,000 crore is required in the next five years for
implementing projects for strengthening and upgradation of the distribution
system.
Distribution reforms, which would be undertaken in each
circle under APDP, include tamper-proof metering at all levels of transmission
in a phased manner, operationalising energy accounting up to 11 kv feeder
level, de-centralised computerised billing and collection, conversion of
existing distribution network into a high voltage distribution system, taking
high voltage line up to the load centre and supplying power through smaller
energy efficient distribution transformers.