Illustrative image – not actual.The Ministry of Power has proposed a relaxation in norms for 25 mega projects that are being implemented at a cost of Rs 1.61 lakh crore.
These projects are being implemented by companies including NTPC, Jindal Power, Reliance Power and Lanco Infratech. The ministry intends to help them avail fiscal benefits under the mega power policy.
For the purpose, the ministry has asked the Cabinet Committee on Economic Affairs (CCEA), to allow the developer to increase the deadline from 36 months to 60 months to sign the power purchase with distribution companies, and to allow tax benefits proportionate to the tied-up capacity.
In addition to this, it has also sought a reduction in the amount of generating capacity to be tied up through competitive bidding to 65 per cent from 85 per cent for 15 of these plants.
If implemented, the proposal will benefit the last lot of mega power plants with a total of 32,330 MW capacity.