Illustrative image – not actual.The power ministry has planned an investment outlay of Rs.40,460.10 crore for 2008-09. This includes internal extra budgetary resources of central public sector undertakings (CPSUs) amounting to Rs.34,460.10 crore and gross budgetary support of Rs.6,000 crore. The net non-plan outlay for the current fiscal is Rs.75 crore.
In outcome budget of the power ministry, NTPC's outlay of Rs.13,588 crore will result in commissioning of 1,320 MW (Sipat I). The outlay will also result in substantial physical progress of the projects scheduled to be commissioned during XIth Plan period.
The National Hydro-electric Power Corporation (NHPC) has outlay of Rs.4,385.19 crore which will be largely used for ongoing schemes such as Subansiri lower, Uri II, Parbati II, Parbati III, Sewa II, Chamera III, Nimoo Bazgo, Chutak, Kishenganga and Teesta Lower Dam III & IV and new proposed projects of Kotlibhel 1A 1B and II.
The outlay for Damodar Valley Corporation will have an outlay of Rs.6,612.65 crore which will result in commercial operation of Meija unit VI (250 MW). In addition, unit VII and VIII (500 MW) of Chandrapura thermal power stations (extension) will also get synchronised. Letter of Award for new projects like Koderma stage I (1,000 MW), Durgapur steel thermal project (1,000 MW), Raghunathpur thermal project (1,200 MW) has already been placed in 2007-08.
Under the Rajiv Gandhi Gramin Vidyutikaran Yojana, the power ministry has set the target of electrification of 25,000 un-electrified villages and offering electricity connections to around 60 lakh below poverty line (BPL) households in 2008-09.
In the transmission sector, the PowerGrid Corporation of India, which is the central transmission utility, has an outlay of Rs.8,040 crore to commission 5,500 circuit km of transmission lines involving 6,285 MVA of transformation capacity.