Power ministry eases bid norms for transmission servicesIllustrative image – not actual.

The power ministry has amended the guidelines for tariff-based competitive bidding for transmission service which were notified on 13 April 2006 under the provisions of the Electricity Act, 2003.

The ministry, which has already invited bids for 14 transmission projects, has amended these guidelines in a bid for attracting private sector investments in the transmission sector. According to the amended guidelines:

  • The transmission service provider (TSP) will enter into a Transmission Service Agreement (TSA) with the concerned utilities. These may include the utilities falling in the region where the load is located, any intervening region and the inter-regional transmission lines between the regions.
  • The bid document for the concerned project will provide a draft of proposed TSA.
  • The successful bidder will be designated as the TSP after executing the TSA and acquiring the special purpose vehicle (SPV).
  • The TSP will seek transmission license from the appropriate Regulatory Commission, if it is not a deemed licensee.
  • The TSA will be effective from the date of grant of license from the appropriate Regulatory Commission. The bid evaluation stage, ratio of minimum and maximum transmission charge (including both the non-scaleable component and the scaleable component incorporating escalation as per index being used for the purpose of evaluation) over the term of the license will not be less than 0.7 to avoid excessive front loading or back loading during the period of contract.
  • The TSA proposed in the request for proposal (RFP) stage may be amended based on the inputs received from bidders during the pre bid conference and it will be made available to all RFP bidders. No further amendments will be carried out in the TSA.
  • The RFP will also specify the Discount Factor (DF) that will be used for evaluation of bids. Besides, the RFP will also specify the bid bond as well as the Contract Performance Guarantee that the bidders will have to furnish. The RFP will also specify the liquidated damages that will apply in event of delay in start of providing the transmission services.
  • The Empowered Committee will constitute a committee for evaluation of the bids with at least one representative from Central Electricity Authority and not less than two representatives from the concerned Regional Power Committees with at least one representative from every concerned RPC and one independent member. The independent member shall have expertise in financial matter/bid evaluation.