The Union Power Ministry has convened a meeting of state government officials, Central Electricity Authority representatives and chief of lending institutions, on 5 March 2003, with a view to expediting the implementation of pending power projects.

 

All the power projects that have been awarded techno-economic clearance between August 1999 and October 2002 have been held up for some reason or the other. In all, there are 40 projects with a total capacity of 23,000 MW, whose implementation has been delayed. Of these, the government has identified nine projects (with total capacity of 4,287 MW) where the likelihood of progress is high.

 

Some of the nine short-listed projects include Maheshwar Hydel Project (Madhya Pradesh), Vishnuprayag Hydel Project (Uttaranchal), BPL Ramagundam Thermal Project and Jagrupadu Thermal Project (both Andhra Pradesh).

 

Power projects in Andhra Pradesh have a higher likelihood of achieving financial closure due to the state government’s proposed policy of offering incentive-based security mechanism instead of an escrow cover.

 

← All latest storiesBack to top →