Power Grid Corporation has received approval from the board of directors for its proposal to invest in expansion and upgradation works by 2016.

 

The company has proposed to invest Rs 1,915.51 crore for expansion and upgradation works.  Following are the details:

 

          
  • investment of Rs 908.08 crore and Rs 539.82 crore for two transmission system strengthening schemes in the northern region
 
  • expansion and upgradation of load despatch centres at a cost of Rs 56.18 crore
 
  • substation work for the NTPC power plant at an estimated cost of  Rs 167.40 crore
 
  • system strengthening programme for the southern region at a cost of Rs 243.53 crore

 