Power Grid earmarks Rs.5,181 crore for strengthening networkIllustrative image – not actual.

Power Grid Corporation of India's (PGCIL) Board of Directors have approved the investment proposals worth Rs.5,181 crore to strengthen its transmission network in the southern, northern and western grid. The investments are spread over the next 36 months. The details of the investment proposals are:

  • Transmission system associated with Tuticorin JV Thermal Power Station at an estimated cost of Rs.353.57 crore with commissioning schedule of 36 months
     

  • System Strengthening -IX in Southern Regional Grid at an estimated cost of Rs.120.62 crore with commissioning schedule of 36 months
     

  • Northern Region System Strengthening scheme-XIII at an estimated cost of Rs.317.69 crore with commissioning schedule of 33 months
     

  • Northern Region System Strengthening scheme-XIV at an estimated cost of Rs.132.19 crore with commissioning schedule of 30 months
     

  • Northern Region System Strengthening scheme-XVII at an estimated cost of Rs.210.79 crore with commissioning schedule of 30 months
     

  • Northern Region System Strengthening scheme-XIX at an estimated cost of Rs.410.29 crore with commissioning schedule of 36 months
     

  • Western Region System Strengthening scheme-X at an estimated cost of Rs.664.96 crore with commissioning schedule of 36 months
     

  • Western Region System Strengthening scheme-XI at an estimated cost of Rs.409.50 crore with commissioning schedule of 36 months
     

  • Northern Region System Strengthening scheme-XV at an estimated cost of Rs.520.48 crore with commissioning schedule of 33 months
     

  • Northern Region System Strengthening scheme-XVIII at an estimated cost of Rs.509.66 crore with commissioning schedule of 33 months
     

  • Transmission system associated with HEP at an estimated cost of Rs.184.19 crore with commissioning schedule of 33 months
     

  • 765kV system for Central part of the Northern Grid – Part I at an estimated cost of Rs.1347.32 crore with commissioning schedule of 36 month