Power Grid Corpn’s board clears investment proposalsIllustrative image – not actual.

Power Grid Corporation’s board has approved investment proposals worth Rs 472.58 crore.

 

The details include:

 

  Unified Real Time Dynamic State Measurement (URTDSM) Project, at an investment of Rs 374.63 crore, with commissioning schedule of 27 months from the date of investment approval; and             
  Transmission System associated with contingency plan for evacuation of power from IL&FS (2x800 MW) at an estimated cost of Rs 97.95 crore, with commissioning schedule of 18 months from the date of investment approval

 

 

URTDSM scheme to be implemented phasewise, involves placement of PMUs at all lines in HVDC terminal stations, 400 kV and above voltage level substations, generating station stepped up at 220 kV level along with provision of FO connectivity and communication equipments.

← All latest storiesBack to top →