Power Grid Corpn of India acquires Bikaner-II Bhiwadi TranscoIllustrative image – not actual.
The Power Grid Corporation of India (PGCIL) has acquired Bikaner-II Bhiwadi Transco (BBTL), the project SPV to establish Transmission System Strengthening Scheme for evacuation of power from solar energy zones in Rajasthan (8.1 GW) under Phase-II Part-F, on build, own, operate and maintain (BOOM) basis from the bid process coordinator -- PFC Consulting. 
 
The transmission system comprises establishment of a new 400 kV switching substation, STATCOM, and substation extension works in Rajasthan and also comprises 400 kV DIC transmission lines which traverse in Rajasthan and Haryana. 
 
The transmission system is an inter-state transmission system project and to be completed in 18 months. Prior to the acquisition, PGCIL had no interest as regards related party transaction. 
 
BBTL has been acquired by the company pursuant to its emerging as the successful bidder under tariff-based competitive bidding. BBTL is engaged in the business as that of POWERGRID i.e. transmission of power. 
 
BBTL was incorporated on 12 May 2020 by the bid process coordinator as per the guidelines encouraging competition in development of transmission projects and tariff-based competitive bidding guidelines for transmission service notified by the Ministry of Power (MoP). 
 
Requisite approvals were obtained by the bid process coordinator for transfer of BBTL. Approval for grant of transmission license and adoption of transmission charges are to be obtained from the Central Electricity Regulatory Commission by BBTL after the acquisition by POWERGRID. 
 
The entity was acquired for aggregate value of around Rs 20.50 crore including 10,000 equity shares at par at Rs 10 each along with assets and liabilities of the company as on the acquisition dated 25 March 2021. 
 
However, the acquisition price is subject to adjustment as per the audited accounts of the company as on the acquisition date.