Parliamentary Panel has opined that the Power Ministry’s target of adding 1
lakh MW of power generating capacity over the next ten years is unrealistic.
The opinion is based on the fact that the
Power Ministry has not made any concrete funding patterns to be able to garner
the massive investment needed to meet the target.
The present rate of capacity addition
is also not too encouraging. The original target of adding 40,245 MW of power
capacity during the Ninth Plan (1997-2002) has already been revised to 24,309
MW in July 1999 during the mid-term review. As against this downsized target,
actual power generation is expected to be in the region of only 21,654 MW.
The slippage of targets derives from
unwarranted reliance on private sector projects. Even the public sector is
blameworthy to a certain extent. For instance, seven projects of NTPC that were
scheduled for completion in the Ninth Plan, have transcended to the Tenth Plan.
The Panel also observed that there is a
growing disparity between the thermal to hydel power generation ratio in India.
Compared with an ideal ratio of 60:40, the on-going ratio in India is 80:20.
The Panel has emphasized the need for increasing hydel power generation, maintaining
that only 17 per cent of India’s hydel power potential of 1.5 lakh MW has so
far been exploited.