The planned capacity addition for power generation in the first year of the Tenth Plan has been missed with the addition of only 69 per cent of the target.
As against the set target of 4,087 MW, a capacity addition of only 2,858 MW has been achieved.
The non-commissioning of the 1,444 MW Dabhol power project phase II, due to the ongoing dispute between Enron Development Corporation and Maharashtra State Electricity Board (MSEB), has been the main reason to missing the target.
Of the total capacity added during the said period, 1,210 MW was in central projects and 1,100 MW in the state sector. The private sector added only 548 MW.