Illustrative image – not actual.Arcelor-Mittal has gained local support from Orissa's Keonjhar district for its proposed 12 million tpa steel plant and hopes to take possession of the required land by end 2008. The pre-land acquisition process has already been successfully initiated.
A total of 7.750 acres of land is required by the company for the proposed Rs.40,000 crore project. Of the total land required, about 6,000 acres of land will be needed for the steel plant, 1,000 acres for the captive power plant and about 750 acres for the township.
From the total land identified for the project, about 2,500 acres of land is government land and the rest belonged to private entities. About 10 per cent of the area was identified as forest land and the government had initiated the process for conversion as per the laid down procedures.
The construction for the project, to be taken up in two phases, will commence once the land is acquired and the first phase of 6 million tpa capacity plant will be completed in four years.
Also See:
Arcelor Mittal allotted 7,750 acres for Orissa steel project (12-Feb-08)
Related Links:
Project profile