Illustrative image – not actual.The Union Ministry of Water Resources has agreed to release Rs 2,000 crore as interim funding for execution of Polavaram Irrigation Project (PIP).
The government of Andhra Pradesh had sought release of Rs 10,000 crore as final clearance for the Revised Cost Estimates (RCE). It is essential for the release of the approved funds, but is expected to take some more time.
Even though the Technical Advisory Committee (TAC) of the Central Water Commission (CWC) cleared the RCE of Rs 55,548 crore of the project in February 2019, it is yet to get the financial concurrence.
The government has already spent close to Rs 4,550 crore over and above the approved costs (as per an old detailed project report), and has been waiting for reimbursement.