Andhra Pradesh Chief Minister N Chandrababu Naidu has revised the completion deadline of the Polavaram Irrigation project to June 2020 from the earlier schedule of December 2019.
The supply of water by gravity from the partially complete Polavaram project in 2019 has been ruled out.
Unless there is a massive flood in Godavari river of 15-16 lakh cusecs, the authority won’t be able to supply water by gravity. However, it will be able to store around 23 tmc ft of water at the project and utilise it downstream.
An amount of Rs 16,000 crore has been spent on the project. Of the total, the state government’s share is over Rs 5,000 crore. Of the remaining Rs 11,000 crore, the Centre still has to release Rs 4,600 crore to the state. An amount of Rs 2,992 crore was required towards land acquisition.
Over 70 percent of the work has been completed.
The two coffer dams will be completed this season while the project spillway and spill channel works will also be done to the maximum.