Illustrative image – not actual.
PNC Infratech has announced that it has received a provisional certificate from the National Highways Authority of India (NHAI) for road projects implemented by its subsidiary company PNC Triveni Sangam Highways.
The provisional certificate is for a length of 119.788 km out of the total project length of 145.066 km from the independent engineer (SA Infrastructure Consultants).
The project's scope includes a six-lane stretch of NH-2 from Chakeri to Allahabad from km 483.687 to km 628.753 in Uttar Pradesh as part of NHPD Phase-V on hybrid annuity mode (HAM).
The project's appointed date was 12 January 2019, with a 910-days construction schedule and a 15-year operation period after completion.