The Pune Metropolitan Region Development Authority (PMRDA) is targeting to complete 25 percent work of the Hinjewadi-Shivajinagar Metro Line III by the end of December 2023.
The route is expected to fully operation by April 2025. The nodal agency has completed 20 percent of work for this entirely elevated Metro line.
The barricading work would be undertaken phase-wise to avoid inconvenience to the citizens. Barricades from the Wakad to Veritas stretch have been reduced and phase-wise barricading will be carried out going ahead.
Moreover, no-parking and no halting on the Baner-Ganeshkhind stretch has not been implemented properly yet, while construction of alternative routes to start University flyover was also pending.
Pothole repair work undertaken by the civic authorities is 80 percent done on this stretch. Allied work on the proposed double-deck flyover at University Chowk is unlikely to be completed by January 2024.