Prime Minister Narendra Modi launched two projects in Jammu and Kashmir, aimed at benefiting the people by way of improved power supply, employment generation and infrastructure creation.

The PM inaugurated Kishanganga Hydroelectric Project and laid the foundation stone for Pakal Dul Power Project on 19 May 2018.

Once completed, the 1,000 MW Pakal Dul Power Project will be the largest hydro power project in the state. In addition, it is the first storage project in the state. As per CCEA sanction, the project cost is Rs 8,112.12 crore.

The project will lead to additional generation of 650 MU in downstream projects as it is a storage type project. It will also improve water availability during a lean season.

The project will be implemented in 66 months from the date of commencement. It will provide direct employment for around 3,000 during construction phase. During the operation phase around 500 people will be employed directly/indirectly.

Apart from this, the state government will get 12 percent free power after 10 years of commissioning of the project and water usage charges as applicable. Additional one percent free power will go towards Local Area Development Fund (LADF). Also, the state government has first right to purchase balance power of NHPC (49 percent) and PTC (two percent).

Furthermore, roads and bridges will be improved under this project.

The Kishanganga Hydroelectric Project of 330 MW is located in Bandipora district of Jammu and Kashmir. On 3 March 2018, all the units of the project were sychronised. The annual generation of the project is 1,712.96 MU.

The project cost is Rs 5,882 crore. The hydro electric project will provide free power of 13 percent to the state, which will be around Rs 133 crore per year.

Around 1,850 local persons were employed during the construction stage and 750 local persons during operation stage through direct and indirect employment.

The project was handed over to NHPC for execution by the state government after an memorandum of understanding (MoU) was signed between state government and the Ministry of Power in July 2000.

 