The inauguration ceremony was performed for Lucknow Metro Rail Corporation’s (LMRC) Phase 1A, underground extension constructed by TATA Projects led joint venture (JV).
The 3.68 km Hussainganj-Hazratganj extension passes through Lucknow and its bustling areas. Work on Lucknow Metro 1A line commenced on April 2016 and was expected to be completed by April 2019.
However, the project was completed before schedule. The new metro line includes stations such as Hussainganj, Sachivalaya and Hazratganj in Uttar Pradesh.
The project involved tunnelling under thickly inhabited areas with heritage structures. The construction of tunnel below Haider Nallah was executed with a clearance of merely 970 mm.
The Delhi Metro Rail Corporation (DMRC) inaugurated its first line extension which was also constructed by TATA Projects led JV.
The Dilshad Garden-Ghaziabad New Bus Adda elevated extension (9.63 km) includes a 170 mtr bridge across the Hindon River.
Work on the project began on December 2014 and includes stations such as Shahid Nagar, Raj Bagh, Rajender Nagar, Shyam Park, Mohan Nagar, Arthala, Hindon and New Bus Adda.
This is the first metro line to reach the interiors of Ghaziabad which will benefit commuters traveling to Delhi for work or other purposes.
Moreover, the stations have also been planned differently with two separate small buildings on either side of the alignment.