Illustrative image – not actual.Petronet LNG Ltd (PLL) plans to invite global bids for EPC contractors for its 2.5 million tonne Kochi LNG terminal.
Earlier, the company had floated global pre-qualification tenders for setting up the terminal on a BOOT basis. Six companies were even shortlisted for this purpose. However, these companies were not too keen to work on the terms and conditions laid down by PLL and final terms and conditions for the contract could not be determined. As a result, PLL has decided to invite global bids for the project once again.
Once PLL’s board approves of this decision, the bid documents, which are being prepared, would be issued. The entire bidding procedure right from the pre-qualification to the final selection of the EPC contractor would be completed by March 2002.
The terminal, which is expected to take three years to construct, is scheduled to receive its first LNG ship in 2005.