Petronet LNG (PLL), a consortium of oil and gas major, has proposed to double its LNG capacity from the current five million metric tonne per annum (MMTPA) to 10 MMPTA, entailing an investment of Rs.787 crore. The PLL board would finalise its expansion programme in the meeting to be held in the middle of March 2004.

The feasibility study including technical and marketing aspects for the proposed expansion programme is in an advanced stage. The detailed reports would shortly be ready.

The company would start the work on erection of another LNG tank and developing other infrastructure for the expanded capacity by July 2004. The terminal with the expanded capacity would be operation within 30 months from the date of commencent of construction of third tank.

 