Illustrative image – not actual.The Planning Commission, on 20 June 2012, gave investment clearance for the Rs 531.01-crore Uderasthan Barrage and other interconnected and interdependent schemes in Bihar.
The project envisages construction of following: (i) Barrage on upstream existing weir, (ii) Right and left head regulators, (iii) Right and left link canals re-sectioning of canals including modernization of canal system by providing lining to reduce conveyance losses, (v) repairs of canals structures repairs/modernisation of inundation canals.
The project shall be completed in 2013-14 and Plan accounts would be closed by 31 March 2014. The project shall be completed in the financial year 2013-14 and Plan accounts would be closed by 31st March 2014. Project may accordingly be executed as per the approved outlays in the State Annual Plans. The State Finance Department would restrict the expenditure to the approved cost and no additional expenditure beyond approved cost may be permitted unless the revised estimate is got approved following the prescribed procedure. The project Authority must seek the approval of the “Command Area Development Plan” form the Planning Commission. Also the CAD works will be executed concurrently with the project implementation so that the participation of the stake holder farmers is ensured right from the stage of project planning through implementation to maintenance.