Pillar work underway on Bhiwandi-Kalyan-Adilabad Bridge projectIllustrative image – not actual.
The Mumbai Metropolitan Region Development Authority (MMRDA) has undertaken construction of six-lane 380.60 mtr bridge across Ulhas creek near Durgadi Fort on Bhiwandi-Kalyan-Adilabad Road (NH-222) in Maharashtra.

Tender was floated in September 2014, inviting contractors to execute the project. However, tenders’ last date of submission got extended several times owing to low response.

MMRDA accorded its administrative approvals for appointment of contractor for the project. In March 2016, Supreme Infrastructure India bagged an order worth Rs 75.72 crore to execute the project and soon work on the project commenced.

In September 2016, Monarch Surveyors & Engineering Consultants bagged an order for project management consultancy (PMC) services and proof checking of designs for the proposed work of construction of the project. However, the work awarded to Supreme Infrastructure in March 2016 was terminated in December 2017.

Following this, in November 2018, tenders were invited for design and construction of balance work for the project. The contract was awarded to T & T Infra for design & construction of balance work of the project in April 2019.

As per information available with Projects Today, pillar work is underway and completion of the project is now re-scheduled for 30 September 2020.