Illustrative image – not actual.The MMRDA has completed around 91 per cent of piling work, as part of the Versova-Andheri-Ghatkopar Metro Line-I spanning 11.7 km.
Out of a total of 1,719 piles, 1,560 have been completed. Also, around 75 per cent work has been completed on the viaduct pile cap & raft, viaduct pier/portal, pier cap casting and pier cap erection. The works of station foundations have reached beyond 75 percent.