Illustrative image – not actual.RPG Group owned Phillips Carbon Black has drawn up a Rs.475 crore capex plan to increase its carbon black capacity and co-generation power production.
Out of the Rs.475 crore capex, Rs.120 crore will be spent for putting up a 30 MW plant at an investment of Rs.120 crore at Durgapur, a 75,000 tpa carbon black plant and a 14 MW co-generation plant at Mundra in Gujarat for Rs.215 crore, expansion of Kochi plant and a 12 MW co-generation plant at a cost of Rs.135 crore. The company has already tied up Rs.210 crore of debt for the project, while Rs.140 crore will come as equity, including Rs.45 crore of preference capital being contributed by the promoters.
The company is also eyeing overseas acquisition in Asian and east European countries.