Illustrative image – not actual.The project worth Rs 250 crore will be implemented in four phases; Phase-I comprises three additional lines. In November 2016, work was completed on Phase-I, work on Phase-II was underway and work was yet to commence on Phase-III and -IV.
In March 2017, work on Phase-II was completed. In January 2018, around 40 percent work was completed on Phase-III.
As per the latest information available with Projects Today, work on Phase-III was nearing completion. The commercial production of Phase-III was likely to commence by November 2019. Work on Phase-IV was still under planning stage. The entire project is slated to be completed by January 2020.